Investment in infrastructure

In 2022, we again invested heavily to create more grid capacity. We made every effort to prevent congestion. The key is to find a balance between investing in new energy infrastructure and ensuring optimal use of our grids, such as by utilising the possibilities of our customers for flexibility in their energy use and consumption. We are closely consulting with our customers on this.

Investments in our grids

The investments we made in our grids in 2022 are part of our 2022-2024 investment plan. This plan sets out our expansion and replacement investments to expand the electricity and gas grids. In 2022, we invested a total of €712 million, of which €700 million was invested in our regulated grids. Consequently, total investments were €25 million higher than in 2021.

Customer-driven investments

Customer-driven investments are made on the request of customers and public authorities (reconstructions). In 2022, these amounted to €252 million, €11 million less than expected (and €16 million less than in 2021), This was due to lower investment in reconstructions. We expect that customer-driven investments will remain high in the coming years, driven in part by the pace of the energy transition and higher energy prices. Both supply and demand are volatile. This makes planning and adjusting these investments more challenging and more important than in the past.

Grid-driven investments

Grid-driven investments are the investments we make to guarantee and improve the capacity and quality of the existing grid. This includes the replacement and reinforcement of stations and grids. Our grid-driven investments in 2022 were €410 million. Financially, this is in line with budget and €59 million more than in 2021. Some of the planned grid-driven investments were delayed due to changes in planning by customers, issues in the environment (for instance, lengthier permitting procedures) and/or lack of materials at contractors. As a result, we were not able to complete the entire planned scope. At the same time, prices rose due to scarcity, so the investments were in line with the budget. Ultimately, we were not able to achieve our target for the realisation of the grid-driven scope for electricity and gas, with scores of 93% and 96% respectively.

Grid-driven investments

Realisation of gas grid

Target

2022

2021

2020

Number of primary gas connections replaced

26,384

22,403

29,040

23,126

Number of gas stations replaced

137

163

127

-

Km of gas pipelines (expansion & replacement)*

Unknown

231

256

227

Km of brittle pipelines replaced

215

200

193

140

Km of brittle pipelines remaining*

1,014

1,046

1,229

1,422

Realisation of electricity grid work

Target

2022

2021

2020

Number of MV installations replaced**

30

19

27

-

Number of complete replacements of connections**

13,428

14,104

12,195

6,065

Realisation of HV / Transmission projects (in numbers)

100%

107%

95%

100%

Realisation of MV / LV projects (in euros)**

100%

89%

76%

Unknown

Number of MV stations (expansion & replacement)*

Unknown

285

432

436

Km of cables (expansion & replacement)*

Unknown

715

998

1,059

  1. * Based on GIS data from early February 2023; information for 2022 is not yet complete due to changes yet to be included.
  2. * Excluding realisation in Zeeland region

Smart meters

In 2022, our investments in smart meters amounted to €34 million, Which was €2 million less than in 2021 and less than budgeted. This was due to the postponement of a major contract from the Ministry of Economic Affairs and Climate Policy relating to the phase-out of the netting scheme for the feed-in of rooftop solar energy. Currently, 84.7% (2021: 82.4%) of households in Stedin’s service area have a smart meter. Under the bill for the phase-out of the netting scheme, a suitable meter will be mandatory. These meters can measure both the supply and the feed-in of electricity separately. At year-end 2022, nearly 87% of all meters in Stedin’s area met the criteria for a suitable meter. This is because there are actually also non-smart meters that display the feed-in as required. However, with these meters, the customer has to manually report the meter readings.

Other assets

Other investments in 2022 amounted to €16 million (€16 million less than in 2021), with €4 million invested in the telecommunications network. Due to the deferral of the investments in steam and heating at NetVerder, investments were €15 million lower than budgeted.

In 2022, Stedin constructed nearly two transformer kiosks per day.

Stedin installed 478 new transformer kiosks in its service area this year. This is at least one new transformer kiosk per day. The reason: more and more people are improving the sustainability of their homes or businesses. Stedin already manages around 26,500 transformer kiosks in Utrecht, Zeeland and Zuid-Holland. In a transformer kiosk, medium voltage is converted to low voltage, suitable for use in the home. They also enable the charging of vehicles in the local area, and they transmit sustainable electricity from the solar panels on people’s roofs. A transformer kiosk is thus an essential hub.

The placement of these kiosks requires careful attention, as not all sites are equally suitable. For example, they have to be placed next to a public road at a central location in the neighbourhood. In addition, they need to be accessible for Stedin fitters to carry out work or fix an outage. Stedin places its transformer kiosks in consultation with the relevant municipality. The neighbourhood is informed when a new transformer kiosk will be placed, and is involved where possible.

Four investments realised in 2022 highlighted:

1. Replacement of main distribution station in Vlissingen-Oost

This station serves large industrial customers in the port. We replaced the obsolete main distribution station and increased the capacity. We installed a 21kV installation in addition to the existing 30kV installation. To connect solar and wind power initiatives to the grid, we realised a complex drilling route of 1.5 km in length and 50 metres deep under the Sloehaven terminal. These initiatives will eventually generate enough renewable electricity for 36,000 households in a year. As such, these projects will achieve 16% and 7% respectively of the remaining target for renewable generation by wind and solar power under the Zeeland Energy Agreement.

2. Expansion of capacity in Broekvelden - Bodegraven

We substantially increased capacity in the area surrounding Bodegraven, laying 10 km of 50kV electricity connections along the A12 between Gouda and Bodegraven. We also expanded the 10kV installation at the Broekvelden station.

3. Kop van de Beer area development - Rotterdam

At Kop van de Beer, the Port of Rotterdam is developing a Food Hub with an area of approximately 60 hectares. The Kop van de Beer is the north-westerly point of the Europoort Port Area. Larger food companies such as Innocent Drinks are setting up production facilities here. We realised a 25/21kV transformer station for the energy supply here that is now in operation.

4. New transformer station - Amersfoort

In Amersfoort, we are working on substantial improvements to four of our stations. We are replacing or removing obsolete components, updating the 50/10kV transformer station and constructing new switching fields. This will both ensure quality and increase capacity for this area. The works for three of the four stations were completed in 2022.

From long-term to medium and short-term investment plans

Changes to the transmission grid take many years to complete. To set these changes in motion in good time, a master plan is needed for the long-term development of Stedin’s electricity grid. We have divided our service area into 18 areas, for which we have formulated a master plan for the period until 2050. The biggest uncertainty is the future development of demand for energy. We try to address this uncertainty by applying available national and Stedin scenarios. To identify the right investments, we compare alternatives using the ‘least regret’ principle. This helps us avoid disposals in situations involving great uncertainty, and also enables us to initiate permitting procedures in good time.

Planned investments

The master plans set the direction for our Strategic Investment Plan (SIP) 2022-2037. We prepare an Investment Plan (IP) based on the SIP once every two years. The IP for 2022-2024 was adopted in April 2022. The available insights on electricity generation from the RES, among other sources, are included in the scenarios. In addition, up-to-date customer information and available recognised regional and national sources, such as effects calculations by the Netherlands Environmental Assessment Agency (PBL), applications under the Sustainable Energy Generation Incentive (SDE++) scheme, as well as public and private property developments, were used in preparing the investment plan. More information on our planned investments in Utrecht, Zeeland and Zuid-Holland is available at www.stedin.net/investeringsplan. An interactive map of our service area, showing the projects we are working on, is available via this link.

RePowerEU

In 2022, while ‘Fit for 55’, the EU’s ambitious climate package, was still going through the policy cycle in Brussels, the European Commission already presented the next climate plan in response to the war in Ukraine and the energy crisis: RePowerEU. REPowerEU aims to reduce dependence on Russian fossil fuels as quickly as possible and includes substantial increases in the European climate targets. The European targets for 2030 include: 45% of total energy use should be renewable, including at least 600GW of solar energy, 35 billion m3 of green gas and 10 million tonnes of renewable hydrogen. These targets will have to be adopted into national policy in the coming years.

Congestion

We work hard to avoid congestion as much as possible. However, we are close to the capacity limit of the TenneT high voltage grid in several parts of the Netherlands. Heavy-use customers in our service area are also affected, in the Port of Rotterdam, Goeree-Overflakkee and the province of Utrecht. Once there is congestion in the high voltage grid, this causes congestion in the relevant area of the regional grid manager. The cooperation with TenneT is thus a crucial issue for us.

TenneT congestion areas

1. Port of Rotterdam and Goeree-Overflakkee

  • Congestion in consumption, study is ongoing

In a large part of the Port of Rotterdam (Europoort, Botlek and Pernis) and the regions of Voorne-Putten, Goeree-Overflakkee, Hoek van Holland and Hoogvliet, Stedin and TenneT are studying whether use of the electricity grid could be improved with congestion management for the consumption of electricity. In these regions, the high voltage grid is virtually at maximum capacity as a result of a growing number of requests for grid reinforcement to enable the electrification of industrial processes and the connection of devices such as electrolysers, e-boilers, shore-side electricity and e-logistics. Collectively, these requests amount to 650 megawatts (MW). Under the various scenarios, this increase was projected to take place only around 2030. This increase of 650 MW is similar to four times the peak capacity of the grid of the city of Delft. TenneT expects to have the results of the congestion management study available in the summer of 2023. The permanent solution is an expansion of capacity for this region, and would involve the addition of three transformer stations. This is expected to be completed between 2027 and 2029. For more information, visit www.stedin.net.

2. Province of Utrecht

  • Congestion for generation, congestion management possible to a certain extent, with the majority placed on a waiting list for transmission rights

  • Congestion in consumption, study is ongoing

Congestion in the province of Utrecht was announced in 2021 due to transmission restrictions by TenneT. The congestion management study showed that capacity could be made available for a large part of our waiting list to offer feed-in capacity (>3x80 amperes) in response to new customer requests. In consultation with our customers - in waiting list order - we discuss how much capacity has been freed up for feed-in. TenneT also issued a pre-announcement for structural congestion for consumption of electricity in November 2022. TenneT is studying the possibilities for congestion management and expects to have the results available in the summer of 2023. TenneT also expects to resolve the current bottlenecks with works to expand the high voltage grid in 2029. There have been requests for 265 MW in transmission capacity in the province of Utrecht in the past two years. This is comparable to the peak demand of the city of Utrecht. For more information, visit www.stedin.net/utrecht.

New code for congestion management

The regulator, the Authority for Consumers and Markets (ACM), published new regulations for the application of congestion management on 25 May 2022. These new regulations give Stedin more possibilities to deal flexibly with supply and demand for energy at locations where the grid is at maximum capacity until the expansion of the grid is realised. This means we can use the limited available room in the electricity grid more efficiently and make room available for new customers, such as producers of green electricity.

The new rules also mean that producers that generate sustainable energy on a large scale for a financial reward participate in congestion management. If the supply of or demand for electricity in an area is greater than the grid can provide, the grid manager can appeal to market parties on the GOPACS platform to reduce or increase their electricity use or generation. These parties then indicate the price at which they are prepared to do this. If the grid manager then accepts their offer, the producer or user fulfils their commitment and receives a financial payment for this.

Status in the three Stedin congestion areas

Stedin did not announce any new congestion area in its own regional grid in 2022.

1. Dordtse Kil

  • Congestion for generation, re-examination in progress

Since September 2021, new sustainable projects at the Dordtse Kil III and IV industrial estates have not been able to feed the energy they have generated into the electricity grid. This will again be possible once the grid expansion is completed (in mid-2025). The new congestion management code offers us more possibilities for congestion management. Accordingly, Stedin initiated a request to the market on 10 November. This will free up room in the electricity grid and possibly enable us to connect more customers. We expect the review in response to the new congestion management code to be completed in the first quarter of 2023. For more information, visit www.stedin.net/dordtsekil.

2. Middelharnis

  • Congestion for generation, re-examination in progress

At peak times in Middelharnis, almost three times as much electricity is generated as is used. As a result, we need to transmit a large volume of generated electricity off the island. More than €100 million has been invested in this over the past ten years, and we will invest just under €7 million more on installing additional transformers in the coming years. The review in response to the new congestion management code will be completed in the first quarter of 2023. Additional room for new feed-in is expected to be available from the beginning of 2024, as the additional transformers will be in operation by then. For more information, visit www.stedin.net/middelharnis.

Preventing congestion in Middelharnis

There was a peak in the feed-in from Middelharnis and the surrounding area on Saturday 19 March, due to the large amount of solar and wind energy generated and very low use of electricity. With such peaks, there is a high risk of a grid overload resulting in an outage. We immediately contacted a producer of solar and wind power, which immediately reduced its production. We were thus able to prevent an outage with the help of this producer.

3. Zeeland: Schouwen-Duiveland and Tholen

  • Congestion for generation, re-examination in progress

A notification of structural congestion was issued for Schouwen-Duiveland and Tholen in the autumn of 2020. We are working on solutions to strengthen the electricity grid here in collaboration with TenneT. To this end, we are installing new transformers in both Schouwen-Duiveland and Tholen, linked to a new 150kV connection to Bergen op Zoom to replace the existing 50kV Noordring. This is expected to be in operation by mid-2027. We are also calling on parties in this area to exercise flexibility, in return for a fee. This has now led to a first contract with Zeeuwind for the Noordpolder wind park. For more information, visit www.stedin.net.

In Schouwen-Duiveland and Tholen, we are running a pilot project with a ‘Non-Firm Connection and Transmission Agreement’. Under this agreement, we can connect customers in areas subject to congestion, but they have no guarantee that they can always feed electricity into our grid and/or purchase energy from our grid. We agree with the customer that their production installation will feed less electricity into the grid or none at all if the grid is at risk of overloading.

First contract for flexible electricity capacity under the new grid code is signed

On 25 November, Stedin, sustainable energy cooperative Zeeuwind and Gabri Hoek B.V. signed the first congestion management contract in the Netherlands for the Noordpolder wind park based on the new electricity grid code. This will mean that structural congestion in the electricity grid can be avoided and potentially 10 megawatts of additional capacity can be created in the local electricity grid for Tholen and Schouwen-Duiveland. This will benefit everyone in the area until the permanent grid expansion is realised in 2027, as it contributes to security of supply. The Noordpolder wind park receives a payment for the flexibility services it provides. This cooperation should be the first in a series of many subsequent flexibility contracts.

Waiting list

As a result of congestion, 228 businesses and institutions were on our waiting list at year-end 2022 for connections amounting to 194 MW (In Utrecht, 141 customers are on the list, in Zuid-Holland 47 and in Zeeland 40). In the case of 188 of the 228 businesses on the waiting list, the request is for feed-in, with 40 waiting for consumption of electricity with a capacity of 40 MW. In our service area, we have 99.9959% supply security. The customers on the waiting list, however, have supply security of 0% of their request. We very much regret the fact that we are not able to provide any new transmission capacity. We make every effort to avoid congestion and operate our grids as efficiently as possible.

Impact of congestion

Where congestion management is not an option, congestion in all areas applies only to heavy-use customers with a connection with a capacity exceeding 3x80 amperes. Consumers can continue to install solar panels and feed electricity into the grid. If congestion management is possible, we make agreements with customers that they will use the grid to a lesser extent at specific times. This creates room for other customers, so that they will in principle not experience problems due to congestion. The scale of congestion management is subject to a maximum. Customers with whom agreements are made receive compensation for this.

Preventing shortage of transmission capacity

Flexibility

If we foresee a problem in our grid due to a specific request, we discuss with the customer what they wish to take up and/or generate. We show the customer what is possible, put things into perspective and discuss about whether or not to apply flexibility in order to reduce peaks in electricity consumption. For customers who agree to flexibility, we work with ‘capacity limiting’ contracts. Customers receive financial compensation for this flexibility.

Expenditure on flexible control power capacity

To be able to apply flexible control power capacity in practice, various agreements have to be made between Stedin and the party offering this flexible control power capacity, including agreements on the fee for this. This is a difficult area. Firstly, the fee has to be sufficient to be attractive to participants - they should not lose out. On the other hand, in the context of a fixed budget, the cost of flexibility directly affects the number of customers that can be connected by means of congestion management. The higher the cost of flexible control power capacity, the fewer customers on the waiting list can be helped and obtain capacity again. Stedin has opted for cost-based fees to compensate customers for the use of flexible control power capacity. This means that when the output of a solar park is reduced, customers receive a fee from Stedin equal to the revenue they would have received for the sale of energy on the day-ahead market.

GOPACS

GOPACS is a collective platform of the regional and national grid managers on which they can collectively and efficiently purchase, align and coordinate flexibility. The platform aligns with existing trading platforms on which participating parties in a specific grid area indicate the price at which they are willing to consume more or less electricity or feed more or less into the electricity grid. As soon as there is a risk of congestion in the grid, the grid manager calls for flexible capacity to be made available. The past year saw a marked increase in the number of participants in the platform.

GOPACS accounted for 721 connections divided between 27 trading companies in 2022. In our service area, those were 219 (2021: 150) connections and 7 trading companies. This year, for all grid managers including TenneT, GOPACS delivered nearly 182 GWh in flexibility with a ‘value’ of more than €59.5 million (2021: 140 GWh / €35 million). The ‘value’ in this case is the difference between buy and sell orders (so what the grid manager pays). As a result of the new congestion management code, we expect to use GOPACS more frequently in future.

Flexchallenge

In April this year, we initiated a market consultation entitled the ‘Stedin Flexchallenge’. This entails an invitation by us to businesses to work with us to use the electricity grid more efficiently. They can do this by purchasing or feeding in more or less electricity at peak times.

The Flexchallenge currently focuses on two areas in which we want to learn various things:

  1. The Spijkenisse grid area. Here, we are exploring the possibilities for avoiding or delaying grid reinforcement by facilitating the gradual increase in demand for electricity.

  2. Congestion area in Schouwen-Duiveland and Tholen In this area, we are studying whether the use of flexible power could create room for new large-scale solar or wind initiatives for the generation of electricity during periods of congestion.

Our appeal has led to 30 solutions from a wide range of parties, falling roughly into three categories: flexibility in sustainable generation by solar and wind, flexible business processes, and storage. In both these areas, Stedin sees opportunities for genuinely creating greater capacity in the electricity grid.

In the second half of 2022, Stedin undertook subsequent steps to make agreements with those organisations offering solutions that can be deployed immediately. In 2022, this led to the first signed contract for the supply of flexibility. Stedin continues to work on contracting more flexibility, so that sufficient flexible capacity is made available to connect customers on the waiting list.

Energy Collective of Businesses in Utrecht

On the initiative of the Energy Collective of Businesses in Utrecht (Energie Collectief Utrechtse Bedrijven, ECUB), an active collaboration was set up between Stedin, the municipality of Utrecht and the province of Utrecht in early 2022. The aim is to achieve optimal use of the grid. This collaboration with local affiliated businesses has led to a collective solution at the Lage Weide industrial estate that prevents the local grid getting overloaded and developments being slowed down or coming to a halt. Together with the ECUB, these businesses have set up a local energy cooperative to offer flexibility in consumption and/or feed-in at peak times and thus collectively make use of this free capacity. The parties are linked up in a virtual grid and share capacity with each other. Peak demand is avoided as much as possible by flexible power demand (through solutions such as smart management of e-charging installations and thermal energy storage). If there is a peak in demand anyway, the available grid capacity is supplemented with energy from batteries and, if necessary, with local fossil-fuel generating capacity, such as a gas generator. With a combination of real-time measurements, smart management and peak generation facilities, we make the best possible use of the available grid capacity.

Use of our grids

Besides flexibility, we have several other tools designed to achieve maximum use of the existing energy grid. Stedin is developing various initiatives for this that will not endanger reliability of supply. Examples include dispensing with the failure reserve, and cable pooling.

Dispensing with the failure reserve and generation management

If a power cable fails and the failure reserve is no longer available to divert electricity, we work with generation management. This concerns the decentralised and remote use of a control box to manage generation capacity (of solar and wind) in case of failures or maintenance works. This service enables us to temporarily reduce production at large-scale generators such as solar and wind parks. In case of a failure, this means we can still use the failure reserve and limit the duration of the failure. This ensures that the high level of reliability of our electricity grid is maintained. Stedin developed its generation management service together with commercial partners and customers Sunrock, Kieszon and Eneco. Sunrock and Eneco are working this year for the first time with a control box in the areas of the Europoort and Dordtse Kil. In Dordtse Kil, this control box is especially useful in helping to prevent an outage in case of a failure. We installed control boxes at three customers in 2022. Now that we have connected two large wind parks (Kroningswind and Harde Zeewering), we can manage more than 200 MW. Our aim is to install control boxes at 500 customers in 2023. From next year, this service will also be made suitable for batteries.

Cable pooling

Cable pooling enables us to use a single cable to accommodate power generated from both and wind and solar on a single connection. This is important, in view of the limited utilisation of the total capacity of a connection in the case of generation plants for solar (12%) and wind (28%). After all, the wind does not always blow and the sun is not always out. The connection must nevertheless be able to cope with periods of peak load. Cable pooling enables us to curtail the output of the solar or wind farm at peak times, when the capacity of the connection is not sufficient. This limits the amount of energy that is lost. As a result, we can increase the capacity utilisation of a connection to 39%, fewer connections are needed and we can absorb more generating capacity on the grid. In 2022, we can see that the market is not yet at the point where cable pooling between different parties is applied in Stedin’s area. However, we expect that this option will become increasingly attractive due to scarceness of capacity.

The interdependence of parties in new initiatives is still cited as an obstacle, as well as caution on the part of financiers. After all, unknown is unloved. An example of the realisation of the technical and economic benefits of cable pooling is the cable pooling ‘light’ project by Vattenfall, which opened this year at Goeree-Overflakkee, combining wind, solar and batteries.

Easing of cable pooling regulations

Several customers have indicated that they wish to make use of cable pooling in situations where a generator and a user are involved. This is however not permitted under current regulations, which state that cable pooling may only occur in combinations of solar and wind. Solar and wind are indeed often complementary. An easing of the cable pooling regulations for generators and users (including battery operators) would be attractive to Stedin and its customers for better use of our grid capacity. For better division of the ‘one-way traffic (generation only)’, we would then be able to use a larger part of the grid for ‘two-way traffic (generation and use)’ with the same infrastructure. Since generation and use are complementary, parties would not have to reduce their generation in periods of strong wind or sunshine, contrary to the situation for cable pooling between generators only. This would make mutual agreements easier to achieve.

Via the National Action Programme for Grid Congestion (Landelijk Actieprogramma Netcongestie) and in other ways, Stedin strives to reduce the barriers for its customers and make this easing of regulation legally permissible.

Use of batteries to prevent congestion

Since TenneT’s announcement of congestion in Limburg and Noord-Brabant, we have seen a quadrupling of the number of requests in our service area and ten times the connection capacity for connecting batteries to the regional electricity grid. In 2022, this concerned more than 1350 MW. This equates to more than three times the peak capacity of the grid of the city of The Hague. The challenge is huge, and Stedin is not able to provide this capacity.

Batteries are an important element in the energy system of the future. Smart batteries can be applied within a few minutes to charge or discharge and can thus help to solve and prevent congestion, provided the right conditions are applied. The new requests relating to batteries, on the other hand, require a lot of reserve capacity of the grid instead of easing pressure on the grid at peak times. These parties usually charge a battery when it’s empty, and not automatically when there is a lot of renewable generation, such as from solar. This creates a risk of congestion.

Stedin sees it as its public duty to prevent unnecessary congestion, and therefore prefers to connect only parties who are prepared to enter into agreements. By law, Stedin is not permitted to be selective about connecting customers. However, we take the view that there is a basis for managing this, as we believe that allowing a few parties to block the capacity of the electricity grid is not in the public interest.

We are consulting with battery operators to formulate this approach and establish whether this would be feasible for all parties involved.

Smart investment in our grids

Station HVS-Centrale is the most notable station in The Hague region, as it is housed in a historic building with a grand façade. This station is also located in a densely populated area. In 2023, we will replace the primary installation at the HVS-Centrale and increase capacity by 50%. Because of the limited space at HVS-Centrale, we have developed two large e-houses together with Siemens, which will be placed next to the HVS-Centrale and will temporarily take over the function of the station during the construction works. This will enable us to renovate the existing station safely and to reconnect all the connections in the HVS-Centrale once the works are completed. The e-houses are compact but have all the functionalities of the existing premises. The construction period is relatively short (approximately 1 year). After the renovation of the HVS-Centrale, we will place the e-houses next to other stations.