The coronavirus crisis enables accelerated replacement of cast iron gas mains in Rotterdam
Digging up the street to replace 130 metres of cast iron gas mains at Stadhuisplein in Rotterdam is no easy task between hordes of shoppers and outdoor seating areas that would normally be busy. But in this case, the coronavirus crisis gave us an opportunity.
The municipality of Rotterdam gave approval for the work to go ahead, and the owners of the hospitality venues also enthusiastically helped to clear the terraces. The work in Rotterdam has now been completed.
Replacement of mini-terminal boxes
Each year, we analyse failure trends. This can lead to adjustments in maintenance policy and/or other choices for investments in our grids. Our people then work with our analysts to find a practical solution. An example is the replacement of 'mini-terminal boxes' ('dwergeindsluitingen'), a specific type of terminal box that is widely used in the Delfland area. They use grease as an insulation medium, which can cause short-circuiting if it leaks. It was observed in the field that this caused a relatively high number of failures, prompting calls to examine suitable alternatives. Repeated failures highlighted the need to prioritise this issue. We are now in the process of replacing 135 terminal boxes. This should result in fewer failures in medium-voltage installations, which can cause serious damage.
Increasingly smarter deployment of service engineers
Our service engineers do more than just remedy failures; they also carry out maintenance on our energy grids. Smarter planning enables us to increasingly deploy our fitters for the construction and replacement of parts of our grid, alongside their maintenance activities. This work, which is carried out to a high technical standard, allows us to maintain and develop the qualities of our technicians, which in turn is useful when dealing with failures.
High-voltage projects
Stedin is involved in a large number of projects related to high voltage. More solar farms have been connected and high-voltage stations modified to transport the energy that is generated from decentralised locations. We have also begun the necessary preparations for the connection enabling CO2 reduction through storage beneath the North Sea (Porthos), for example. Another large project is the reconstruction of a dyke strengthening programme in Krimpenerwaard. In order to ensure the interests of the water authority, Oasen, Stedin and the municipality remain closely aligned, we have entered into a cooperation agreement. In 2020, significant progress was made for environmental management and the preparation of the call for tenders.
High voltage on Energy Island
Middelharnis, or 'Energy Island', as it is also known, is a major hub for renewable energy generation. The capacity of the wind farms there is projected to be roughly 225 MW at the start of 2022. There are also several large-scale and small-scale solar farms, with a capacity of approximately 200 MW.
In order to cope with these vast amounts of electricity, Stedin began work on a major expansion of the high-voltage station in Middelharnis in 2010. Four large transformers and four new 50 kV switching installations have been constructed in phases. Two 150 kV connections have also been laid to the Rotterdam port area. These two additional connections are needed in case of an overcapacity of electricity generation on sunny and windy days. This overcapacity of electricity will then be routed to the Rotterdam port area. Such overcapacity of electricity generation is easily reached, when one considers that the power consumption of Middelharnis itself (on days without any sun or wind) is a maximum of 35 MW.
The penultimate phase of this investment in the grid will be completed in 2021. The last phase will be completed by mid-2023.
Investments in our grids
Our investment levels have increased year on year since 2017. In 2020, we invested a total of €620 million, of which €613 million was invested in our regulated grids. Total investments were consequently €26 million lower than in 2019, at 93% of what was planned for 2020. Growth slowing down in 2020 was largely attributable to the coronavirus crisis. This had a negative impact on the planned grid-driven investments as well as our investments in smart meters.
As part of the five-year efficiency programme, we were able, by improving our work efficiency and making our investments more risk-based, among other things, to achieve a saving of more than €10 million as well as €3 million in one-off savings in 2020.
Customer-driven investments
Customer-driven investments in 2020 amounted to €272 million: €12 million higher than budgeted and €18 million more than in 2019. These are the investments we make at the request of customers. Investments remained high in all areas, such as the high volume of new home buildings, the growth in the field of improved sustainability (charging point connections, solar farms, etc.) and the increase in terms of public authority-driven reconstructions. It is our expectation that the customer-driven investments will remain substantial in the coming years, increasingly driven by the pace of the energy transition. At the same time, COVID-19 has led to increased social and economic uncertainty. This trend, taken as a whole, makes planning and adjusting investments more challenging and even more important than in the past.
Grid-driven investments
Our grid-driven investments in 2020 were €276 million. This is €39 million less than budgeted and €18 million more than in 2019. The planned grid investments were hit by delay as a result of the COVID-19 crisis. Grid-driven investments are the investments that are made to guarantee and improve the capacity and quality of the existing grid.
Regarding gas replacements, more than 21,968 primary gas connections (target: 23,000), 97 NEN 1059 control stations (target: 117) and over 139 kilometres of cast iron pipelines (target: 150 km of pipelines) were nonetheless replaced.
We partly attained our target as regards electricity replacements through the replacement of 76 COQ/MIPAK stations (target: 86). Remediation work at customers' homes was delayed due to COVID-19. In addition, we decided proactively to put off investments in the light of evolving customer demand, which is not expected to have an impact on our network for the time being.
Smart meters
Our investments in smart meters in 2020 were €48 million, which is €19 million less than budgeted. Smart meters was where we saw the most direct impact from COVID-19, due to the decision to suspend work at customers' homes early on in the crisis. The long-term target for 80% of all households to have a smart meter by the end of 2020 was nonetheless achieved in part of our service area. It is expected that we will have installed smart meters in more than 80% of homes across our entire service area by the first half of 2021. You can read more about this topic in 'High-quality products and services'.
Other assets
The other investments in 2020 were €24 million, which is a reduction of €35 million compared with 2019. This difference is attributable to the substantial investment in our property at Nijverheidsweg in Utrecht in 2019 in accordance with our strategic real estate plan. Limited additional investments in the construction of the Stedin Telecom Network were also made in 2020.
Investment plan
All of the grid managers prepared an investment plan for the first time in 2020. The investment plan is intended to replace the Quality and Capacity Documents, which were previously drawn up every two years for the Netherlands Authority for Consumers and Markets (ACM). The Investment Plan 2022-2022 sets out the expansion and replacement capital expenditure planned for the electricity and gas grids. The investment plan details how we will ensure sufficient capacity for the distribution of electricity and gas in the next three years and how these distribution services will be provided safely. The plan was made available for consultation for four weeks, to give the opportunity for comments on the proposed investments. The consultation took place as follows:
In total, eight opinions were submitted to Stedin and four to Enduris. The submitted opinions from the consultation and our response to them were added to the investment plan. The plan was also submitted to the Netherlands Authority for Consumers and Markets (ACM). Following assessment by the ACM, the final investment plan was adopted and published on 1 October 2020.
As not all the regional energy transition plans were available for the 2020-2022 investment plan in Stedin's service area, recognised regional and national available sources, such as calculations of the effects by the PBL Netherlands Environmental Assessment Agency, applications under the Sustainable Energy Generation Incentive (SDE+) scheme and public and private property developments, were used for the investment plan.
Future-proof energy supply for Utrecht Science Park
Utrecht Science Park is the largest science park in the Netherlands and houses hospitals, universities of applied sciences, Utrecht University and various research institutions. It accommodates more than 27,00 staff members and 51,000 students. The science park is attracting an increasing number of centres of expertise, such as the Netherlands National Institute for Public Health and the Environment (RIVM). As this development is accompanied by a rising demand for energy, Stedin laid a third 50 kV connection to Utrecht Science Park in 2020. A third transformer will be added in 2021 to expand the energy supply capacity. Once the work is completed, the science park will be assured of a reliable energy supply and sufficient capacity.
Main investment results
The investments in the working area of Stedin and Enduris that stood out the most in 2020 were made for grid reinforcement or with the aim of facilitating maximum utilisation of grid capacity. Further information on these investments can be found in the section on 'Facilitating the energy transition'. The three projects concerned are advance investment in a main distribution station in Borsele, Station Europoort in Rotterdam and the expansion of five transformer stations in Zoetermeer.
To ensure continuing support in society for the substantial task inherent in the energy transition, the grid managers face the major challenge of becoming increasingly transparent and of constructing future electricity stations or carrying out grid reinforcements. The maps on the following pages for the provinces of Utrecht, Zeeland and South Holland show the planned investments in electricity for stations and connections (>25 kV) that will be undertaken or commenced in the period 2020-2022. The expected year of completion is indicated for each project. The maps are focused on grid expansion.
Planned investments in electricity for stations and connections (>25 kV) undertaken or commenced in 2020-2022.
What is the average cost of a station in terms of money, time and space?
A station covers between 200 and 10,000 m2. It takes between 2.5 and 5 years to construct a station, at a cost of €1.5 million to €10 million, excluding land purchase costs. Installing the connection takes between 6 months and 3 years, at a rough estimate, and costs €100 to €1,000 per metre.
Stedin will invest €784 million in expanding the electricity grid in the period 2020-2022. Enduris will invest €86.9 million. Expansion capital expenditure accounts for 41-48% of the total investments that will be made. In 2021, we will invest €15,549,000 in the province of South Holland and €25,440,000 in the province of Utrecht in capacity expansions, which will be technically ready in the same year. This excludes DNWG, Telecom, NetVerder and other Stedin investments.
New station New reinforced connection Expansion |